KB Khurda-Balangir line: fast progressing - to be completed by 2027
Posts: 1,655
Threads: 813
Joined: Dec 2020
Reputation:
1
As per
https://x.com/OdishaRail/status/1929178365501591798 and
https://x.com/OdishaRail/status/1929178752581316676
Quote: T2 tunnel has achieved breakthrough marking a special moment as now all seven tunnels are in various stages of construction of Khurda Balangir line.
T2 tunnel is 1775 metres long with a curve in it.
Posts: 1,655
Threads: 813
Joined: Dec 2020
Reputation:
1
Yesterday , 05:25 PM
(This post was last modified: 7 hours ago by Chitta .)
Latest status
of various segments and stations:
Balangir (302)
Bichhuapali (286.258) - operational (Weekly new18421 Puri-Sonepur express , Daily 12893/4 extended. )
Jhartarbha (275.608) - operational (Weekly 18421 Puri-Sonepur express , Daily 12893/4 extended. )
Narsinghgarh - NSGR (old name - Khambeswarpalli) (264.208) - operational (Weekly 18421 Puri-Sonepur express , Daily 12893/4 extended. )
Sonepur (253.908) - operational (PM inaugurated on 2nd Feb 2024 and introduced Weekly 18421 Puri-Sonepur express , Daily 12893/4 extended. ).
Purnapani (244.558) - operational https://www.youtube.com/watch?v=u5qq4LZO...uDaniVlogs , nov 25, 2023 https://www.youtube.com/watch?v=aGlnueXI...imodalNews , Signal testing on March 29, 2024 https://twitter.com/OdishaRail/status/17...6416747727 , CRS inspection on June 15th 2024 https://www.youtube.com/watch?v=IzjASa4w...=ARVEEVLOG , https://www.youtube.com/watch?v=XQJGbLDA...TRAVELVLOG
Jharmunda (224.158) - operational https://www.youtube.com/results?search_q...munda+rail ; https://www.youtube.com/watch?v=5iIlRHm6...uDaniVlogs , Oct 11, 2023: https://twitter.com/EastCoastRail/status...p_TLQ&s=19 , Dec 16, 2023 https://www.youtube.com/watchv=VV5uvUHTb...=ARVEEVLOG , Matrch 30 2024 Engine Run: https://www.youtube.com/watch?v=9foIworQ...imodalNews , July 17 2024 CRS completed https://www.youtube.com/watch?v=Qfr0JITJ...=ARVEEVLOG
Boudh (207.888) - operational https://www.youtube.com/results?search_query=Boudh+rail + , https://www.youtube.com/watch?v=nEf9Ui1h...imodalNews , https://www.youtube.com/watch?v=p_HPo8ak...uDaniVlogs , https://www.youtube.com/watch?v=zhMehUQ8...=ARVEEVLOG , May 3 2024 https://www.youtube.com/watch?v=WdcQCIa_...nPutelVlog , Jun 14th 2024: https://www.youtube.com/watch?v=pNcYU9ne...njuVlogger , June 17th 2024 https://www.youtube.com/watch?v=Dt5sGtQl...=ARVEEVLOG , June 30th 2024 https://www.youtube.com/watch?v=MYBm6tNy...=ARVEEVLOG , Aug 17, 2024: CRS completed https://pragativadi.com/another-mileston...missioned/
Champapur (194.187) - operational https://www.youtube.com/results?search_q...r+Balangir , March 31 2024 rails placed near station that is being built: https://www.youtube.com/watch?v=iqWTn4fV...=ARVEEVLOG , July 10, 2024 https://www.youtube.com/watch?v=vlGcO0Sv...=ARVEEVLOG ; Engine rolling done September 28th 2024 See https://x.com/OdishaRail/status/1840395600484823372
Puranakatak (180.75) - operational https://www.youtube.com/results?search_q...ay+station ; https://www.youtube.com/watch?v=8mkXO4Xc...BzdGF0aW9u ; https://www.youtube.com/watch?v=nEf9Ui1h...imodalNews ; https://www.youtube.com/watch?v=TQ_kbFj_...uDaniVlogs , October 9, 2023: https://twitter.com/EastCoastRail/status...G823w&s=19 ; Feb 28, 2024: https://www.youtube.com/watch?v=ew0EEQdj...imodalNews ; April 18, 2024: https://www.youtube.com/watch?v=8yN-QcdH...=Dilsebiju , June 15 2024: https://www.youtube.com/watch?v=0DqK0MN2...=Dilsebiju , July 9 2024 https://www.youtube.com/watch?v=Qf1Lc9mI...=ARVEEVLOG ; Engine rolling done on September 29th 2024 https://www.youtube.com/watch?v=yUxN6mw1...mahibevlog
Towards Charichak : July 20 2024: https://www.youtube.com/watch?v=cb8-Y0cp...=ARVEEVLOG
Tunnel T7: With a length of 1975 meters, Tunnel T7 extends from Km 168+528.1 to Km 170+501.7. (Tunneling completed on August 20, 2024 https://kalingatv.com/odisha/ecor-reache...e-project/ )
Charichak (167.4) - Forrest clearance received in Feb 2023 ; https://www.youtube.com/watch?v=dGrmPtfs...=ARVEEVLOG ( Expected to be completed by 2026-27 )
Station work: May 22, 2025 https://www.youtube.com/watch?v=VjER5paG...mahibevlog Tunnel T6: With a length of 315 meters, Tunnel T6 extends from Km 165+000.6 to Km 165+279.8.Tunnel T5: Tunnel T5 covers a distance from Km 164+464 to Km 164+780.68, spanning 317 meters: done https://pragativadi.com/khurda-road-bala...e-by-2026/ Tunnel T4: This engineering marvel stretches from Km 156+231.5 to Km 160.415, boasting an extraordinary length of 4185 meters, there’s also a 700-meter escape tunnel ensuring safety.
Two viaducts (1.3 kms and 0.55 kms): From https://sambadenglish.com/latest-news/od...ce-8647814 : May 2025 status of Charichak Harbhanga road viaduct near Karanjkata village https://www.youtube.com/watch?v=Jj1gkQrcOko ; June 17 2025 status: https://www.youtube.com/watch?v=vk-NxyOMDTA
Adenigarh (153.75) - Forrest clearance received in Feb 2023 ; https://www.youtube.com/watch?v=65dng_qo...=ARVEEVLOG ; March 29 2024 Tunnel construction initiated https://www.youtube.com/watch?v=hooyRrHj...=ARVEEVLOG (Expected to be completed by 2026-27 )
Baniguchha (139.75) - Forrest clearance received in Feb 2023 (Expected to be completed by 2026-27 )
Tunnel T3 (2,620 mtr length, ch 126.420 km to ch 129.040
Two viaducts (#302 of 4.8kms and 0.29 kms): From https://sambadenglish.com/latest-news/od...ce-8647814 . The 4.8 km one will be the second longest rail viaduct in India and as per https://www.constructionworld.in/transpo...026-/75174 is expected to be complete by August 2026.
Buguda (121.8) - Forrest clearance received in Feb 2023 : September 15 2023 - https://www.youtube.com/watch?v=XW8we3se...imodalNews , March 31 2024 ground work https://www.youtube.com/watch?v=6j1OB_rR...=ARVEEVLOG (Expected to be completed by 2026-27 )
Tunnel T2 (1775 M Length, Km 108.225 To Km 110.000): Tunnel breakthrough on June 1 2025; all tunnels have breakthrough now : https://x.com/OdishaRail/status/1929178365501591798
Tunnel T1 (800 M Length, Km 106.825 To Km 107.625):
Dasapalla (105.875) - operational (From Jan 2024 ) (https://erail.in/train-enquiry/18424 , https://erail.in/train-enquiry/08556 )
Nuagaon Road (90.43) - operational (https://erail.in/train-enquiry/08423 and https://erail.in/train-enquiry/08429 )
Mahipur (77.38) - operationa l (https://erail.in/train-enquiry/08423 and https://erail.in/train-enquiry/08429 )
Nayagarh town (65.456) - operational (https://erail.in/train-enquiry/08423 , https://erail.in/train-enquiry/08429 , https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423 )
Bolgarh Road (54.32) - operational (https://erail.in/train-enquiry/08423 , https://erail.in/train-enquiry/08429 , https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423 )
Rajsunakhala (41.5) - operational (https://erail.in/train-enquiry/08423 , https://erail.in/train-enquiry/08429 , https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423 )
Begunia (32) - operational (https://erail.in/train-enquiry/08423 , https://erail.in/train-enquiry/08429 , https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423 )
Khurda Town (13.35) - operational (https://erail.in/train-enquiry/08423 , https://erail.in/train-enquiry/08429 , https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423 )
Khurda Rd (0)
Posts: 1,655
Threads: 813
Joined: Dec 2020
Reputation:
1
Yesterday , 05:28 PM
(This post was last modified: Yesterday , 05:29 PM by Chitta .)
Attached Files
Thumbnail(s)
Users browsing this thread: 1 Guest(s)